Senate Bill No. 274–Committee on Commerce and Labor

 

CHAPTER..........

 An ACT relating to contractors; revising the provisions governing the rights and duties of contractors and subcontractors under contracts and subcontracts; and providing other matters properly relating thereto.

 

THE PEOPLE OF THE STATE OF NEVADA, REPRESENTED IN

SENATE AND ASSEMBLY, DO ENACT AS FOLLOWS:

 

1-1    Section 1. Chapter 624 of NRS is hereby amended by adding thereto

1-2  the provisions set forth as sections 2 to 9, inclusive, of this act.

1-3    Sec. 2.  As used in NRS 624.610, 624.620 and 624.630 and sections 2

1-4  to 9, inclusive, of this act, the words and terms defined in sections 3 and

1-5  4 of this act have the meanings ascribed to them in those sections.

1-6    Sec. 3.  “Higher-tiered subcontractor” means a subcontractor under

1-7  a contract who has entered into an oral or written subcontract with

1-8  another subcontractor pursuant to which the other subcontractor has

1-9  agreed to perform any of the duties of the subcontractor under the oral

1-10  or written subcontract.

1-11    Sec. 4.  “Lower-tiered subcontractor” means a subcontractor who

1-12  has agreed in an oral or written contract to perform any of the duties of

1-13  another subcontractor under another oral or written subcontract.

1-14  Sec. 5.  1.  Except as otherwise provided in this section, if a

1-15  contractor or higher-tiered subcontractor enters into:

1-16  (a) A written subcontract with a subcontractor that includes a

1-17  schedule for payments, the contractor or higher-tiered subcontractor

1-18  shall pay the subcontractor:

1-19      (1) On or before the date payment is due; or

1-20      (2) Within 10 days after the date the contractor or higher-tiered

1-21  subcontractor receives payment for all or a portion of the work, labor,

1-22  materials, equipment or services described in a request for payment

1-23  submitted by the subcontractor,

1-24  whichever is earlier.

1-25  (b) A written subcontract that does not contain a schedule for

1-26  payments, or a subcontract that is oral, the contractor or higher-tiered

1-27  subcontractor shall pay the subcontractor:

1-28      (1) Within 30 days after the date the subcontractor submits a

1-29  request for payment; or

1-30      (2) Within 10 days after the date the contractor or higher-tiered

1-31  subcontractor receives payment for all or a portion of the work, labor,

1-32  materials, equipment or services described in a request for payment

1-33  submitted by the subcontractor,

1-34  whichever is earlier.

1-35    2.  If a contractor or higher-tiered subcontractor has complied with

1-36  subsection 3, the contractor or higher-tiered subcontractor may:

1-37    (a) Withhold from any payment owed to the subcontractor:

1-38      (1) A retention amount that the subcontractor is authorized to

1-39  withhold pursuant to the contract;

1-40      (2) An amount equal to the sum of the value of:


2-1         (I) Any work or labor that has not been performed or materials

2-2  or equipment that has not been furnished for which payment is being

2-3  sought; and

2-4         (II) Costs and expenses reasonably necessary to correct or repair

2-5  any work which is the subject of the request for payment and which is

2-6  not materially in compliance with the subcontract to the extent that such

2-7  costs and expenses exceed 50 percent of the amount withheld pursuant to

2-8  subparagraph (1); and

2-9       (3) The amount the owner, contractor or higher-tiered

2-10  subcontractor has paid or is required to pay pursuant to an official notice

2-11  from a state agency or employee benefit trust fund, for which the owner,

2-12  contractor or higher-tiered subcontractor is or may reasonably be liable

2-13  for the subcontractor or his subcontractors in accordance with chapter

2-14  608, 612, 616A to 616D, inclusive, or 617 of NRS; and

2-15    (b) Require as a condition precedent to the payment of any amount

2-16  due, lien releases furnished by the subcontractor and his lower-tiered

2-17  subcontractors and suppliers. For purposes of this paragraph:

2-18      (1) If the amount due is paid with a check or is not paid

2-19  concurrently with the contractor’s or higher-tiered subcontractor’s

2-20  receipt of the lien releases, the lien releases must be conditioned upon the

2-21  check clearing the bank upon which it is drawn and the receipt of

2-22  payment and shall be deemed to become unconditional upon the receipt

2-23  of payment; and

2-24      (2) The lien releases must be limited to the amount of the payment

2-25  received.

2-26    3.  If, pursuant to subparagraph (2) or (3) of paragraph (a) of

2-27  subsection 2 or paragraph (b) of subsection 2, a contractor or higher-

2-28  tiered subcontractor intends to withhold any amount from a payment to

2-29  be made to a subcontractor, the contractor or higher-tiered subcontractor

2-30  must give, on or before the date the payment is due, a written notice to

2-31  the subcontractor of any amount that will be withheld and give a copy of

2-32  such notice to all reputed higher-tiered subcontractors, contractors and

2-33  the owner. The written notice must:

2-34    (a) Identify the amount of the request for payment that will be

2-35  withheld from the subcontractor;

2-36    (b) Give a reasonably detailed explanation of the reason the

2-37  contractor or higher-tiered subcontractor wiGreen numbers along left margin indicate location on the printed bill (e.g., 5-15 indicates page 5, line 15).ll withhold that amount,

2-38  including, without limitation, a specific reference to the provision or

2-39  section of the subcontract, and any documents relating thereto, and the

2-40  applicable building code, law or regulation with which the subcontractor

2-41  has failed to comply; and

2-42    (c) Be signed by an authorized agent of the contractor or higher-tiered

2-43  subcontractor.

2-44    4.  A subcontractor who receives a notice pursuant to subsection 3

2-45  may provide written notice to the contractor or higher-tiered

2-46  subcontractor of the correction of a condition described in the notice

2-47  received pursuant to subsection 3. The notice of correction must be

2-48  sufficient to identify the scope and manner of the correction of the

2-49  condition and be signed by an authorized representative of the

2-50  subcontractor. If a contractor or higher-tiered subcontractor receives a


3-1  written notice from the subcontractor of the correction of a condition

3-2  pursuant to this subsection, the contractor or higher-tiered subcontractor

3-3  must:

3-4    (a) Pay the amount withheld by the contractor or higher-tiered

3-5  subcontractor for that condition on or before the date the next payment is

3-6  due the subcontractor; or

3-7    (b) Object to the scope and manner of the correction of the condition,

3-8  on or before the date the next payment is due to the subcontractor, in a

3-9  written statement which sets forth the reason for the objection and which

3-10  complies with subsection 3. If the contractor or higher-tiered

3-11  subcontractor objects to the scope and manner of the correction of a

3-12  condition, he shall nevertheless pay to the subcontractor, along with

3-13  payment made pursuant to the subcontractor’s next payment request, the

3-14  amount withheld for the correction of conditions to which the contractor

3-15  or higher-tiered subcontractor no longer objects.

3-16    Sec. 6.  1.  If a contractor or higher-tiered subcontractor fails to:

3-17    (a) Pay the subcontractor within the time provided in subsection 1 or 4

3-18  of section 5 of this act;

3-19    (b) Pay the subcontractor within 45 days after the 25th day of the

3-20  month in which the subcontractor submits a request for payment, even if

3-21  the contractor or higher-tiered subcontractor has not been paid and the

3-22  subcontract contains a provision which requires the contractor or

3-23  higher-tiered subcontractor to pay the subcontractor only if or when the

3-24  contractor or higher-tiered subcontractor is paid; or

3-25    (c) Give the subcontractor written notice of any withholding in the

3-26  time and manner required by subsection 3 or 4 of section 5 of this

3-27  act,

3-28  the subcontractor may stop work under the subcontract until payment is

3-29  received if the subcontractor gives written notice to the contractor or

3-30  higher-tiered subcontractor at least 10 days before stopping work.

3-31    2.  If a subcontractor stops work pursuant to paragraph (a) or (c) of

3-32  subsection 1, the subcontractor may terminate the subcontract by giving

3-33  written notice of the termination to the contractor or higher-tiered

3-34  subcontractor after stopping work but at least 15 days before the

3-35  termination of the subcontract. If the subcontractor is paid the amount

3-36  due before the date for termination set forth in the written notice, the

3-37  subcontractor shall not terminate the subcontract and shall resume work.

3-38    3.  If an owner, contractor or a higher-tiered subcontractor through

3-39  his own act or neglect, or through an act or neglect of his agent,

3-40  excluding acts of God, floods, fires, labor disputes, strikes or reasonable

3-41  adjustments in work schedules, causes the work to be stopped for a

3-42  period of 15 days or more, the subcontractor may terminate the

3-43  subcontract if:

3-44    (a) The subcontractor gives written notice of his intent to terminate to

3-45  the contractor or higher-tiered subcontractor at least 10 days before

3-46  terminating the subcontract; and

3-47    (b) The contractor or higher-tiered subcontractor fails to allow the

3-48  subcontractor to resume the work within the time set forth in the written

3-49  notice given pursuant to paragraph (a).


4-1    4.  If a subcontractor stops work pursuant to paragraph (a) or (c) of

4-2  subsection 1, the contractor or higher-tiered subcontractor may

4-3  terminate the subcontract by giving the subcontractor written notice of

4-4  his intent to terminate at least 15 days before terminating the

4-5  subcontract.

4-6    5.  If the subcontract is terminated pursuant to subsection 3, or if the

4-7  subcontractor stops work in accordance with this section and the

4-8  subcontract is terminated pursuant to subsection 2 or 4, the

4-9  subcontractor is entitled to recover from the contractor or higher-tiered

4-10  subcontractor with whom he has contracted the amount found by a trier

4-11  of fact to be due the subcontractor, including, without limitation:

4-12    (a) The cost of all work, labor, materials, equipment and services

4-13  furnished by and through the subcontractor, including any profit and

4-14  overhead the subcontractor incurred or earned through the date of

4-15  termination;

4-16    (b) The profit that the subcontractor and his lower-tiered

4-17  subcontractors would have received if the subcontract had been

4-18  performed in full;

4-19    (c) Interest at a rate equal to the rate agreed upon in the subcontract,

4-20  or, if no interest rate is so provided, interest at a rate equal to the prime

4-21  rate at the largest bank in this state, as determined by the commissioner

4-22  of financial institutions on January 1 or July 1, as the case may be,

4-23  immediately preceding:

4-24      (1) The time the subcontract was signed; or

4-25      (2) If the subcontract was oral, the time the terms of the

4-26  subcontract were agreed upon by the parties,

4-27  plus 2 percent; and

4-28    (d) The reasonable costs, including court costs, incurred by the

4-29  subcontractor and his lower-tiered subcontractors in collecting the

4-30  amount due.

4-31  At any action brought to enforce the rights or obligations set forth in this

4-32  subsection, the trier of fact may award reasonable attorney’s fees to the

4-33  subcontractor or, if the trier of fact determines that the subcontractor

4-34  stopped work or terminated the contract without reasonable cause, the

4-35  trier of fact may award reasonable attorney’s fees to the contractor or

4-36  higher-tiered subcontractor.

4-37    6.  If a subcontractor stops work pursuant to this section, each lower-

4-38  tiered subcontractor with whom the subcontractor has contracted who

4-39  has not fully performed under the contract may also stop work on the

4-40  project. If a subcontractor terminates a subcontract pursuant to this

4-41  section, all such lower-tiered subcontractors may terminate their

4-42  contracts with the subcontractor.

4-43    7.  The right of a subcontractor to stop work or terminate a

4-44  subcontract pursuant to this section is in addition to all other rights that

4-45  the subcontractor may have at law or in equity and does not impair or

4-46  affect the right of a subcontractor to maintain a civil action or to submit

4-47  any controversy arising under the contract to arbitration.

4-48    8.  No subcontractor or his lower-tiered subcontractors, or their

4-49  respective sureties, may be held liable for any delays or damages that an

4-50  owner, contractor or higher-tiered subcontractor may suffer as a result


5-1  of the subcontractor or lower-tiered subcontractor stopping his work or

5-2  terminating a subcontract for reasonable cause and in accordance with

5-3  this section.

5-4    Sec. 7.  1.  A subcontractor shall provide a copy of any notice given

5-5  to a contractor or higher-tiered subcontractor pursuant to this section or

5-6  section 5 or 6 of this act to each lower-tiered subcontractor with whom

5-7  the subcontractor has contracted who has not fully performed under the

5-8  contract. Upon receipt of payment pursuant to section 5 of this act, the

5-9  subcontractor shall notify all such lower-tiered subcontractors in writing

5-10  of his receipt of payment.

5-11    2.  A subcontractor shall provide a copy of any notice given to a

5-12  contractor or higher-tiered subcontractor pursuant to this section or

5-13  section 5 or 6 of this act to each reputed higher-tiered subcontractor,

5-14  contractor and the owner, if known. The failure of a subcontractor to

5-15  comply with this subsection does not invalidate any notice otherwise

5-16  properly given.

5-17    3.  A condition, stipulation or provision in a subcontract or other

5-18  agreement which requires a subcontractor to waive any rights provided

5-19  in this section or section 5 or 6 of this act, or which limits those rights, is

5-20  void.

5-21    4.  All notices required pursuant to this section or section 5 or 6 of

5-22  this act must be:

5-23    (a) Delivered personally, in which case the subcontractor shall obtain

5-24  a notarized statement from the person who delivered the notice as proof

5-25  of delivery;

5-26    (b) Sent by facsimile and delivered by regular mail, in which case the

5-27  subcontractor shall retain proof of a successful transmission of the

5-28  facsimile;

5-29    (c) Delivered by certified mail; or

5-30    (d) Delivered in the manner provided in the contract.

5-31    5.  Within 5 days after a contractor receives a written request for the

5-32  information set forth in paragraphs (a), (b) and (c) from a subcontractor

5-33  with respect to a subcontract that has not been fully performed, the

5-34  contractor shall notify the subcontractor in writing of the following:

5-35    (a) The date the contractor made a specified payment to his

5-36  subcontractor;

5-37    (b) Whether the contractor has paid his subcontractor the entire

5-38  amount of a specified payment; and

5-39    (c) The amount withheld by the contractor of a specified payment to

5-40  his subcontractor and the reason for the withholding.

5-41    Sec. 8.  1.  Except as otherwise provided in subsections 2 and 4 and

5-42  subsection 4 of section 9 of this act, if an owner of real property enters

5-43  into a written or oral contract with a contractor for the performance of

5-44  work by the contractor, the owner must:

5-45    (a) Pay that contractor on or before the date a payment is due

5-46  pursuant to a schedule for payments established in a written contract; or

5-47    (b) If no such schedule is established or if the contract is oral, pay the

5-48  contractor within 21 days after the date the contractor submits a request

5-49  for payment.

5-50    2.  If an owner has complied with subsection 3, the owner may:


6-1    (a) Withhold from any payment to be made to the contractor:

6-2       (1) A retention amount that the owner is authorized to withhold

6-3  pursuant to the contract;

6-4       (2) An amount equal to the sum of the value of:

6-5         (I) Any work or labor that has not been performed or materials

6-6  or equipment that has not been furnished for which payment is being

6-7  sought; and

6-8         (II) Costs and expenses reasonably necessary to correct or repair

6-9  any work which is the subject of the request for payment and which is

6-10  not materially in compliance with the contract to the extent that such

6-11  costs and expenses exceed 50 percent of the amount withheld pursuant to

6-12  subparagraph (1); and

6-13      (3) The amount the owner has paid or is required to pay pursuant

6-14  to an official notice from a state agency or employee benefit trust fund,

6-15  for which the owner is or may reasonably be liable for the contractor or

6-16  his subcontractors in accordance with chapter 608, 612, 616A to 616D,

6-17  inclusive, or chapter 617 of NRS; and

6-18    (b) Require as a condition precedent to the payment of any amount

6-19  due, lien releases furnished by the contractor and his subcontractors and

6-20  suppliers. For purposes of this paragraph:

6-21      (1) If the amount due is paid with a check or is not paid

6-22  concurrently with the owner’s receipt of the lien releases, the lien

6-23  releases must be conditioned upon the check clearing the bank upon

6-24  which it is drawn and the receipt of payment and shall be deemed to

6-25  become unconditional upon the receipt of payment; and

6-26      (2) The lien releases must be limited to the amount of the payment

6-27  received.

6-28    3.  If, pursuant to subparagraph (2) or (3) of paragraph (a) of

6-29  subsection 2 or paragraph (b) of subsection 2, an owner intends to

6-30  withhold any amount from a payment to be made to a contractor, the

6-31  owner must give, on or before the date the payment is due, a written

6-32  notice to the contractor of any amount that will be withheld. The written

6-33  notice must:

6-34    (a) Identify the amount of the request for payment that will be

6-35  withheld from the contractor;

6-36    (b) Give a reasonably detailed explanation of the reason the owner

6-37  will withhold that amount, including, without limitation, a specific

6-38  reference to the provision or section of the contract, and any documents

6-39  relating thereto, and the applicable building code, law or regulation with

6-40  which the contractor has failed to comply; and

6-41    (c) Be signed by an authorized agent of the owner.

6-42    4.  A contractor who receives a notice pursuant to subsection 3 may

6-43  provide written notice to the owner of the correction of a condition

6-44  described in the notice received pursuant to subsection 3. The notice of

6-45  correction must be sufficient to identify the scope and manner of the

6-46  correction of the condition and be signed by an authorized representative

6-47  of the contractor. If an owner receives a written notice from the

6-48  contractor of the correction of a condition pursuant to this subsection,

6-49  the owner must:


7-1    (a) Pay the amount withheld by the owner for that condition on or

7-2  before the date the next payment is due the contractor; or

7-3    (b) Object to the scope and manner of the correction of the condition,

7-4  on or before the date the next payment is due to the contractor, in a

7-5  written statement which sets forth the reason for the objection and which

7-6  complies with subsection 3. If the owner objects to the scope and manner

7-7  of the correction of a condition, he shall nevertheless pay to the

7-8  contractor, along with payment made pursuant to the contractor’s next

7-9  payment request, the amount withheld for the correction of conditions to

7-10  which the owner no longer objects.

7-11    Sec. 9.  1.  A contractor shall provide a copy of any notice given to

7-12  an owner pursuant to subsection 1 or 2 of NRS 624.610 to each

7-13  subcontractor with whom the contractor has contracted who has not fully

7-14  performed under that contract. Upon receipt of payment pursuant to

7-15  section 8 of this act, the contractor shall notify all such subcontractors in

7-16  writing of his receipt of payment.

7-17    2.  A condition, stipulation or provision in a contract or other

7-18  agreement which requires a contractor to waive any rights provided in

7-19  this section, NRS 624.610 or section 8 of this act or which limits those

7-20  rights is void.

7-21    3.  All notices required pursuant to this section, NRS 624.610 and

7-22  section 8 of this act must be:

7-23    (a) Delivered personally, in which case the contractor shall obtain a

7-24  notarized statement from the person who delivered the notice as proof of

7-25  delivery;

7-26    (b) Sent by facsimile and delivered by regular mail, in which case the

7-27  contractor shall retain proof of a successful transmission of the

7-28  facsimile;

7-29    (c) Delivered by certified mail; or

7-30    (d) Delivered in the manner provided for in the contract.

7-31    4.  This section, NRS 624.610 and section 8 of this act do not apply to

7-32  a contract between:

7-33    (a) A residential contractor and a natural person who owns a single-

7-34  family residence for the performance of qualified services with respect to

7-35  the residence; and

7-36    (b) A public body and a contractor for the performance of work and

7-37  labor on a public work.

7-38    5.  Within 5 days after an owner receives a written request for the

7-39  information set forth in paragraphs (a), (b) and (c) from a subcontractor

7-40  with respect to a subcontract that has not been fully performed, the

7-41  owner shall notify the subcontractor in writing of the following:

7-42    (a) The date the owner made a specified payment to his contractor;

7-43    (b) Whether the owner has paid the entire amount of a specified

7-44  payment to his contractor; and

7-45    (c) The amount withheld by the owner from a specified payment to the

7-46  contractor and the reason for the withholding.

7-47    Sec. 10.  NRS 624.020 is hereby amended to read as follows:

7-48    624.020  [1.  For the purpose of this chapter, “contractor”] For the

7-49  purposes of this chapter, unless the context otherwise requires:

7-50    1.  “Contractor” is synonymous with “builder.”


8-1    2.  [Within the meaning of this chapter, a] A contractor is any person,

8-2  except a registered architect or a licensed professional engineer, acting

8-3  solely in his professional capacity, who in any capacity other than as the

8-4  employee of another with wages as the sole compensation, undertakes to,

8-5  [or] offers to undertake to, [or] purports to have the capacity to undertake

8-6  to, or submits a bid to, or does himself or by or through others, construct,

8-7  alter, repair, add to, subtract from, improve, move, wreck or demolish any

8-8  building, highway, road, railroad, excavation or other structure, project,

8-9  development or improvement, or to do any part thereof, including the

8-10  erection of scaffolding or other structures or works in connection

8-11  therewith. Evidence of the securing of any permit from a governmental

8-12  agency or the employment of any person on a construction project must be

8-13  accepted by the board or any court of this state as prima facie evidence that

8-14  the person securing that permit or employing any person on a construction

8-15  project is acting in the capacity of a contractor pursuant to the provisions of

8-16  this chapter.

8-17    3.  A contractor [within the meaning of this chapter] includes a

8-18  subcontractor or specialty contractor, but does not include anyone who

8-19  merely furnishes materials or supplies without fabricating them into, or

8-20  consuming them in the performance of, the work of a contractor.

8-21    4.  A contractor [within the meaning of this chapter] includes a

8-22  construction manager who performs management and counseling services

8-23  on a construction project for a professional fee.

8-24    Sec. 11.  NRS 624.610 is hereby amended to read as follows:

8-25    624.610  1.  If [, through no fault or act of a prime contractor or

8-26  anyone employed by him, the] an owner fails to [pay that contractor:

8-27    (a) Pursuant to their schedule for payments under the contract, or within

8-28  a reasonable time after maturity and presentation of charges if no schedule

8-29  is established;

8-30    (b) Any sum certified by the architect, engineer or other supervisory

8-31  agent of the owner; or

8-32    (c) Such sum as is otherwise properly due, or if] :

8-33    (a) Pay the contractor in the time and manner required by subsection

8-34  1 or 4 of section 8 of this act; or

8-35    (b) Give the contractor written notice of any withholding in the time

8-36  and manner required by subsection 3 or 4 of section 8 of this

8-37  act,

8-38  the contractor may stop work after giving written notice to the owner at

8-39  least 10 days before stopping work. If a contractor stops work pursuant to

8-40  this subsection, the contractor may terminate the contract by giving

8-41  written notice of termination to the owner after stopping work but at least

8-42  15 days before terminating the contract. If the contractor is paid the

8-43  amount due before the date for termination of the contract set forth in

8-44  the written notice, the contractor shall not terminate the contract and

8-45  shall resume his work.

8-46    2.  If theowner throughhis own act or neglect, or through an act or

8-47  neglect of his agent, excluding acts of God, floods, fires [or strikes,] ,

8-48  labor disputes, strikes or reasonable adjustments to work schedules,

8-49  causes the work to be stopped for a period of [5 working] 15 days or more,

8-50  the contractor may[, after 5 working days’] terminate the contract if:


9-1    (a) The contractor gives written notice of his intent to terminate to the

9-2  owner[, stop work or terminate the contract and] at least 10 days before

9-3  terminating the contract; and

9-4    (b) The owner fails to allow work to resume within the time set forth

9-5  in the written notice given pursuant to paragraph (a).

9-6    3.  If a contractor stops work pursuant to subsection 1, the owner may

9-7  terminate the contract by giving the contractor written notice of his intent

9-8  to terminate at least 15 days before terminating the contract.

9-9    4.  If the contract is terminated pursuant to subsection 2, or if the

9-10  contractor stops work in accordance with this section and the contract is

9-11  terminated pursuant to subsection 1 or 3, the contractor is entitled to

9-12  recover from the owner payment [for] in an amount found by a trier of

9-13  fact to be due the contractor, including, without limitation:

9-14    (a) The cost of all work [executed.

9-15    2.  If, through no fault of a subcontractor or anyone employed by him,

9-16  the contractor fails to pay that subcontractor:

9-17    (a) Pursuant to the schedule for payments under the subcontract, or

9-18  within a reasonable time after maturity and presentation of charges if no

9-19  schedule is established;

9-20    (b) Any sum certified by the architect, engineer or other supervisory

9-21  agent of the owner or contractor; or

9-22    (c) Such sum as is otherwise properly due,

9-23  or if the contractor through his own acts or neglect, excluding acts of God,

9-24  floods, fires or strikes, causes the work to be stopped for a period of 5

9-25  working days or more, the subcontractor may, after 5 working days’

9-26  written notice to the owner and the contractor, stop work or terminate the

9-27  subcontract and recover from the contractor payment for all work executed.

9-28  The subcontractor may not be held liable for nonperformance of that

9-29  subcontract and for the cost incurred by the contractor to complete the

9-30  work.

9-31    3.  The provisions of subsection 2 do not apply if the contractor’s

9-32  failure to pay is caused by his need to withhold money pursuant to an

9-33  official notice from a state agency that he is liable to make payments or

9-34  contributions for the subcontractor pursuant to chapter 608 or 612 or

9-35  chapters 616A to 616D, inclusive, or chapter 617 of NRS.] , labor,

9-36  materials, equipment and services furnished by and through the

9-37  contractor, including any profit and overhead the contractor incurred or

9-38  earned through the date of termination;

9-39    (b) The profit that the contractor and his subcontractors would have

9-40  received if the contract had been performed in full;

9-41    (c) Interest at a rate equal to the rate agreed upon in the contract, or if

9-42  no interest rate is so provided, then interest at a rate equal to the prime

9-43  rate at the largest bank in this state, as determined by the commissioner

9-44  of financial institutions on January 1 or July 1, as the case may be,

9-45  immediately preceding:

9-46      (1) The time the contract was signed; or

9-47      (2) If the contract was oral, the time the terms of the contract were

9-48  agreed to by the parties,

9-49  plus 2 percent; and


10-1    (d) The reasonable costs, including court costs, incurred by the

10-2  contractor and his subcontractors in collecting the amount

10-3  due.

10-4  At any action brought to enforce the rights or obligations set forth in this

10-5  subsection, the trier of fact may award reasonable attorney’s fees to the

10-6  contractor or, if the trier of fact determines that the contractor stopped

10-7  work or terminated the contract without reasonable cause, the trier of

10-8  fact may award reasonable attorney’s fees to the owner.

10-9    5.  If a contractor stops work pursuant to subsection 1, each

10-10  subcontractor with whom the contractor has contracted who has not fully

10-11  performed under that contract may also stop work on the project. If a

10-12  contractor terminates a contract pursuant to this section, all such

10-13  subcontractors may terminate their contracts with the contractor.

10-14  6.  The right of a contractor to stop work or terminate a contract

10-15  pursuant to this section is in addition to all other rights that the

10-16  contractor may have at law or in equity and does not impair or affect the

10-17  right of a contractor to maintain a civil action or to submit any

10-18  controversy arising under the contract to arbitration.

10-19  7.  No contractor or his subcontractors, or their respective sureties,

10-20  may be held liable for any delays or damages that an owner may suffer

10-21  as a result of the contractor, subcontractor or lower-tiered subcontractor

10-22  stopping his work or terminating a contract for reasonable cause and in

10-23  accordance with this section or section 6 of this act.

10-24  Sec. 12.  NRS 624.620 is hereby amended to read as follows:

10-25  624.620  1.  Except as otherwise provided in [subsections 2, 3 and 5,]

10-26  this section, any money remaining unpaid for the construction [or

10-27  remodeling of a building] of a work of improvement is payable to the

10-28  contractor within 30 days after:

10-29  (a) Occupancy or use of the work of improvement by the owner or by a

10-30  person acting with the authority of the owner; or

10-31  (b) The availability of a [constructed or remodeled building] work of

10-32  improvement for its intended use. The contractor must have given a written

10-33  notice of availability to the owner on or before the day on which he claims

10-34  that the [building became available.

10-35  2.  The] work of improvement became available for use or occupancy.

10-36  2.  If the owner has complied with subsection 3, the owner may:

10-37  (a) Withhold payment for the amount of [any disputed or uncompleted

10-38  items if he notifies the contractor in writing at the time of withholding as to

10-39  any disputed items.] :

10-40     (1) Any work or labor that has not been performed or materials or

10-41  equipment that has not been furnished for which payment is sought;

10-42     (2) The costs and expenses reasonably necessary to correct or

10-43  repair any work that is not materially in compliance with the contract to

10-44  the extent that such costs and expenses exceed 50 percent of the amount

10-45  of retention being withheld pursuant to the terms of the contract; and

10-46     (3) Money the owner has paid or is required to pay pursuant to an

10-47  official notice from a state agency, or employee benefit trust fund, for

10-48  which the owner is liable for the contractor or his subcontractors in

10-49  accordance with chapter 608, 612, 616A to 616D, inclusive, or chapter

10-50  617 of NRS.


11-1    (b) Require, as a condition precedent to the payment of any [money]

11-2  unpaid amount under the construction contract, that [waivers of] lien

11-3  releases be furnished by the contractor’s subcontractors, suppliers or

11-4  employees. For purposes of this paragraph:

11-5      (1) If the amount due is paid with a check or is not paid

11-6  concurrently with the owner’s receipt of the lien releases, the lien

11-7  releases must be conditioned upon the check clearing the bank upon

11-8  which it is drawn and the receipt of payment and shall be deemed to

11-9  become unconditional upon the receipt of payment; and

11-10     (2) The lien releases must be limited to the amount of the payment

11-11  received.

11-12  3.  If pursuant to paragraph (a) of subsection 2, an owner intends to

11-13  withhold any amount from a payment to be made to a contractor, the

11-14  owner must, on or before the date the payment is due, give written notice

11-15  to the contractor of any amount that will be withheld. The written notice

11-16  must:

11-17  (a) Identify the amount that will be withheld from the contractor;

11-18  (b) Give a reasonably detailed explanation of the reason the owner

11-19  will withhold that amount, including, without limitation, a specific

11-20  reference to the provision or section of the contract, and any documents

11-21  relating thereto, and the applicable building code, law or regulation with

11-22  which the contractor has failed to comply; and

11-23  (c) Be signed by an authorized agent of the owner.

11-24  4.  A contractor who receives a notice pursuant to subsection 3 may

11-25  provide written notice to the owner of the correction of a condition

11-26  described in the notice received pursuant to subsection 3. The notice of

11-27  correction must be sufficient to identify the scope and manner of the

11-28  correction of the condition and be signed by an authorized representative

11-29  of the contractor. If an owner receives a written notice from the

11-30  contractor of the correction of a condition described in an owner’s notice

11-31  of withholding pursuant to subsection 3, the owner must, within 10 days

11-32  after receipt of such notice:

11-33  (a) Pay the amount withheld by the owner for that condition; or

11-34  (b) Object to the scope and manner of the correction of the condition

11-35  in a written statement that sets forth the reason for the objection and

11-36  complies with subsection 3. If the owner objects to the scope and manner

11-37  of the correction of a condition, he shall nevertheless pay to the

11-38  contractor, along with payment made pursuant to the contractor’s next

11-39  payment request, the amount withheld for the correction of conditions to

11-40  which the owner no longer objects.

11-41  5.  The partial occupancy or availability of a building requires payment

11-42  in direct proportion to the value of the part of the building which is

11-43  partially occupied or partially available. For projects which involve more

11-44  than one building, each building must be considered separately in

11-45  determining the amount of money which is payable to the contractor.

11-46  [4.] 6. Unless otherwise provided in the construction contract, any

11-47  money which is payable to a contractor pursuant to this section accrues

11-48  interest at a rate equal to the lowest daily prime rate at the [three largest

11-49  United States banking institutions on the date the contract is executed plus]

11-50  largest bank in this state, as determined by the commissioner of financial


12-1  institutions on January 1 or July 1, as the case may be, immediately

12-2  preceding:

12-3    (a) The time the contract was signed; or

12-4    (b) If the contract was oral, the time the terms of the contract were

12-5  agreed to by the parties,

12-6  plus 2 percent . [,from 30 days after the date on which the money became

12-7  payable until the date of payment.

12-8    5.] 7. This section does not apply to:

12-9    (a) Any residential building; or

12-10  (b) Public works.

12-11  8.  As used in this section, unless the context otherwise requires,

12-12  “work of improvement” has the meaning ascribed to it in NRS 108.221.

12-13  Sec. 13.  NRS 99.040 is hereby amended to read as follows:

12-14  99.040  1.  When there is no express contract in writing fixing a

12-15  different rate of interest, interest must be allowed at a rate equal to the

12-16  prime rate at the largest bank in Nevada, as ascertained by the

12-17  commissioner of financial institutions, on January 1 or July 1, as the case

12-18  may be, immediately preceding the date of the transaction, plus 2 percent,

12-19  upon all money from the time it becomes due, in the following cases:

12-20  (a) Upon contracts, express or implied, other than book accounts.

12-21  (b) Upon the settlement of book or store accounts from the day on

12-22  which the balance is ascertained.

12-23  (c) Upon money received to the use and benefit of another and detained

12-24  without his consent.

12-25  (d) Upon wages or salary, if it is unpaid when due, after demand

12-26  therefor has been made.

12-27  The rate must be adjusted accordingly on each January 1 and July 1

12-28  thereafter until the judgment is satisfied.

12-29  2.  The provisions of this section do not apply to money owed:

12-30  (a) For the construction [or remodeling of a building] of a work of

12-31  improvement pursuant to NRS 624.620; or

12-32  (b) By a contractor to his subcontractor pursuant to NRS 624.630.

 

 